The Black Circle installation team were invited to tender for the fit out of a new bar in Swansea, starting with a large 5 bedroom house. Competing against 2 local construction companies Black Circle proved the most competitive and were instructed to carry out the works.
Numerous existing structural walls were removed and replaced with deep foundations for the new structural steel work, whilst keeping the existing ground floor and 1st floor ceilings complete with the original ornate mouldings. The 1st floors were strengthened to accommodate large public capacity, and doorways
widened to comply with fire regulations. Full internal fit out to include the 2 x bespoke bars. External landscaping works to accommodate a large patio area.
Location
Swansea
Duration
13 weeks
Area
240m2